The PM Surya Ghar subsidy in Gwalior gives every home on an MPMKVVCL domestic connection up to ₹78,000 towards rooftop solar: ₹30,000 for 1 kW, ₹60,000 for 2 kW and ₹78,000 for 3 kW or more. It is paid by the central government into the applicant's bank account after the system is installed by a registered vendor, inspected and fitted with a net meter. Sunvera Energy is registered on the PM Surya Ghar portal and handles the full process for Gwalior families from its office at Kampoo — including the trickier cases of multi-storey houses, separate floors and flats.
How much you get
| System | Subsidy | Price before subsidy | Net cost |
|---|---|---|---|
| 1 kW | ₹30,000 | Quoted after survey | — |
| 2 kW | ₹60,000 | ≈ ₹1.4–1.5 lakh | ≈ ₹80,000–90,000 |
| 3 kW | ₹78,000 | ≈ ₹1.8–2.0 lakh | ≈ ₹1,02,000–1,22,000 |
| 5 kW | ₹78,000 (maximum) | ≈ ₹2.75–3.0 lakh | ≈ ₹1,97,000–2,22,000 |
Madhya Pradesh homes receive the central subsidy; the maximum is ₹78,000 whatever the system size.
Multi-storey houses and flats
Many Gwalior homes in Lashkar, Morar and Thatipur have two or three families on separate floors, each with its own meter. Each domestic connection can apply for its own system and subsidy, provided there is roof space and the owners agree on how it is shared. We draw a roof plan showing each family's panels and run separate cables to each meter. In apartment buildings in City Centre and on the outskirts, individual flat owners need the society's permission to use the roof; where the society installs a plant for common areas, different rules apply, and we explain them at the survey.
Who qualifies
- A domestic MPMKVVCL connection in the applicant's name.
- A roof owned or legally usable by the applicant, with about 100 sq ft of shade-free space per kW.
- No earlier central rooftop subsidy on the same connection.
- A registered vendor and domestically manufactured (DCR) panels.
Shops, clinics, schools and factories do not qualify; they save at higher tariffs instead.
Documents and steps
Keep ready a recent MPMKVVCL bill with the consumer number, the applicant's Aadhaar, a bank passbook or cancelled cheque, a mobile number linked to Aadhaar and roof photos. Then:
- Registration on the portal with your consumer number.
- Feasibility approval from MPMKVVCL.
- Installation by Sunvera Energy in one to two days.
- Installation details uploaded; MPMKVVCL inspection.
- Net meter fitted and commissioning certificate issued.
- Bank details confirmed on the portal; subsidy credited.
Avoiding delays
The most common hold-ups in Gwalior are a bill still in a late parent's name, a mismatch between the bill and Aadhaar spellings, a sanctioned load lower than the system size, and unpaid arrears. We check all four before applying. Load increases are filed alongside the solar application so you do not make separate trips to the MPMKVVCL office.
Zero down payment with the subsidy
Families who prefer not to pay upfront can take a 100% loan through partner banks. The subsidy, once credited, is used to prepay part of the loan, so a 3 kW EMI of about ₹3,000 a month falls to roughly ₹1,800–1,900. We help with the loan papers alongside the PM Surya Ghar application, so both move together.
Get help at Kampoo
Bring your bill, Aadhaar and passbook to our office at Floor 1, Shop 3, Nagar Nigam Market, Kampoo, or WhatsApp photos to +91 77103 07937. Families near Maharaj Bada, in City Centre or Morar can ask for a home visit. Zero down payment finance is available.
Frequently Asked Questions — Solar in Gwalior
Up to ₹78,000. The central subsidy is ₹30,000 for 1 kW, ₹60,000 for 2 kW and ₹78,000 for 3 kW or more, for homes on a domestic MPMKVVCL connection. It is paid into the applicant's bank account after commissioning with a net meter.
Yes, if each has its own domestic connection in its own name and the roof has space for both systems. Each connection applies separately on the portal and receives its own subsidy. We plan a roof layout that shares the space fairly.
A flat owner needs the housing society's permission to use the roof and a domestic connection in their name. Where the society installs solar for common areas, separate rules apply. We explain the options for your building at the survey.
Application to net meter usually takes three to six weeks. After commissioning and bank details are confirmed on the portal, the subsidy is released to your account, typically within a few weeks. We track it for you.
No. PM Surya Ghar is only for domestic connections. Shops, clinics, schools and factories pay the full price but save more per unit at their higher tariffs, and businesses can often claim accelerated depreciation.
Written generation estimate, exact price after subsidy and bank-finance options — no obligation.