How Long Does Rooftop Solar Installation Take? From Enquiry to Subsidy

Residential Solar 📅 30 Oct 2026 ⏱ 5 min read
Technician installing rooftop solar panels

For a typical 2–5 kW home system, the physical installation takes one to three days. The whole journey — from your first call to the subsidy reaching your bank — usually takes six to ten weeks, most of it waiting for DISCOM feasibility, inspection and the net meter. Knowing the stages helps you plan, especially if you want the system working before summer.

Key Takeaways

  • Survey and quotation: a few days.
  • Portal registration and DISCOM feasibility: about one to three weeks.
  • Installation: one to three days for a home system.
  • Inspection and net meter: typically three to five weeks after installation.
  • Subsidy credit: a few weeks after commissioning.

The timeline at a glance

StageWhat happensTypical time
1. Enquiry and bill reviewInstaller reads your bills and suggests a sizeSame day
2. Site surveyRoof measured, shade and structure checkedWithin a few days
3. Quotation and decisionWritten quote with components and price1–3 days after survey
4. Portal registration and feasibilityPM Surya Ghar application, DISCOM technical feasibility1–3 weeks
5. Material dispatchDCR panels, inverter, structure deliveredWithin a week of feasibility
6. InstallationStructure, panels, wiring, earthing, inverter1–3 days
7. Inspection and net meterDISCOM inspects and fits the bi-directional meter3–5 weeks after installation
8. SubsidyCommissioning report, bank details, creditA few weeks after commissioning

Stage by stage

Survey and quotation

The survey checks roof area, orientation, shade from tanks and neighbouring buildings, the roof slab or sheets, the route for cables and the position of the inverter and meter. A good installer gives you a written quotation with a layout, components by make and model, expected generation and the net cost after subsidy.

Registration and feasibility

Your application is registered on the PM Surya Ghar portal against your consumer number, and the DISCOM checks technical feasibility — whether the local transformer and your sanctioned load can take the system. This is the first waiting period. If the sanctioned load is too low, a load increase is applied for now, which can add time.

Installation day

On day one the team fixes the galvanised structure, anchoring it without damaging waterproofing. Panels are mounted, strings wired, and the DC and AC protection boxes, earthing pits and lightning arrester installed. The inverter is mounted and connected, and the system is tested. A 3 kW home system is often finished in a day; larger systems or elevated structures take two to three days. Until the net meter is fitted, the system may be kept off or run according to the DISCOM's rules, which your installer will explain.

Inspection and net meter

The installer uploads installation details and photos, and the DISCOM schedules an inspection. After approval, the bi-directional net meter is installed and the system is commissioned. This is usually the longest wait — typically three to five weeks — and can stretch in busy seasons.

Subsidy

Once the commissioning report appears on the portal, you submit bank details and a cancelled cheque. The subsidy is then credited to your account, usually within a few weeks.

What you need to do at each stage

Most of the work is the installer's, but a few steps need you. Before the survey, keep your last twelve electricity bills and Aadhaar handy, and make sure someone can show the team the roof and the meter. Before registration, check that the meter, applicant and bank account names match. On installation day, keep the roof clear and agree where the inverter will be mounted — a shaded, ventilated wall near the meter is best. After commissioning, upload or hand over the cancelled cheque promptly, and keep copies of the invoice, warranty cards and commissioning report together.

A real example

A family in Gwalior with a 3 kW requirement calls in the first week of December. The survey is done two days later, and they accept the quotation that week. Portal registration and DISCOM feasibility take about two weeks, so the material arrives just before the new year and the system is installed in a single day. The inspection and net meter follow about four weeks later, at the start of February, and the subsidy is credited in early March. The system is fully commissioned well before April, and the winter surplus is already banked against the summer bills.

What can slow things down

  • Sanctioned load lower than the planned system size.
  • Name mismatch between the meter, applicant and bank account.
  • Roof repairs or waterproofing needed before installation.
  • Monsoon rain delaying installation days.
  • Busy seasons at the DISCOM before summer.
  • Incomplete documents uploaded on the portal.

Commercial and larger systems

For shops and small businesses of 10–25 kW, installation takes a few days, and approvals follow a similar path without the subsidy step. Larger plants of 50 kW and above need structural checks, a single-line diagram and electrical-inspector approval, and installation can take one to three weeks depending on size and roof type. Planning them around the business's working hours and shutdowns keeps disruption low.

When to start

If you want the system working by April, start by December or January. Winter installation also means net metering banks the good winter generation, while household use is low, for use in the hot months.

Our timeline

Sunvera Energy handles every stage, from survey to subsidy, for customers of MPMKVVCL, MPPKVVCL and CSPDCL, and keeps you updated at each step. WhatsApp your last electricity bill to +91 77103 07937 to get a written quotation and a timeline for your system.