Solar installation and commissioning is where a good design either becomes a safe, productive system or a source of problems for 25 years. This page explains, step by step, what Sunvera Energy's installation teams do on your roof, the electrical tests every system must pass before it is switched on, how the DISCOM inspection and net meter fit in, and what you receive at handover. It applies to homes, shops, institutions and industrial plants across Madhya Pradesh and Chhattisgarh.
Before the team arrives
Installation starts after the design is approved and, for subsidy and net-metering projects, after DISCOM feasibility. The customer is told the date, how many people will come, roughly how long they will be on the roof and whether a short power shutdown is needed for the tie-in. Materials — panels, inverter, structure, cables, protection boxes and earthing material — are checked against the design and the serial numbers recorded, because the PM Surya Ghar portal and warranties need them. The roof should be clear of stored items and, if repairs or waterproofing were planned, finished beforehand.
Step by step on site
- Marking out — the array layout is marked on the roof, keeping walkways, drains and tank access clear.
- Structure — galvanised legs and rails are anchored with chemical anchors into RCC or ballasted, or clamped to sheet profiles without drilling on industrial roofs; everything is aligned to the design tilt and squared.
- Modules — panels are lifted carefully (never carried by the cable), clamped with the correct torque and kept clear of footsteps.
- DC wiring — strings are connected with matched MC4 connectors and UV-rated solar cable, routed in conduit and clipped so wind cannot whip it.
- DC box and inverter — the DC distribution box with fuses, isolator and SPD is mounted near the inverter, which goes on a shaded, ventilated wall close to the meter.
- AC side — AC distribution box with breaker and SPD, then the tie-in to the building's main board.
- Earthing and lightning — dedicated earth pits, bonding of all metalwork, and a lightning arrester with its own earth.
- Labelling and clean-up — isolators and boxes labelled, debris removed, the roof left as found.
The tests before switch-on
| Test | Why it matters |
|---|---|
| Polarity check on every string | Reversed polarity can damage the inverter on first connection |
| Open-circuit voltage (Voc) per string | Confirms every module is connected and the string is within inverter limits |
| Short-circuit or operating current per string | Reveals a weak module, bad connector or shading problem |
| Insulation resistance of DC cables | Detects damaged insulation that could cause leakage or fire |
| Earth resistance of each pit | Confirms a safe path to ground for faults and surges |
| Inverter functional and grid-sync test | Confirms correct start-up, output and anti-islanding shutdown when the grid is off |
Results are recorded in the commissioning report. Any string that does not match the others is investigated before handover, not left for the owner to discover.
DISCOM inspection and net meter
For grid-connected systems, the installation is uploaded on the PM Surya Ghar portal or the DISCOM's system, and MPMKVVCL, MPPKVVCL or CSPDCL schedules an inspection. The inspector checks the installation against the approved capacity, protection devices, earthing and anti-islanding, and the bi-directional meter is fitted afterwards. Sunvera attends the inspection and corrects any observations on the spot where possible. For larger commercial and industrial plants, electrical-inspector approval is obtained before energisation. Until the net meter is installed, the system may be kept switched off or limited as per DISCOM rules.
What you receive at handover
- Commissioning report with all test results
- Serial numbers of panels and inverter, invoices and warranty documents
- Single-line diagram and, for larger plants, as-built drawings
- Monitoring app access, set up on the owner's phone
- Owner training — reading the inverter display and app, safe shutdown, cleaning, and what to do in a fault
- Subsidy status for PM Surya Ghar projects, with next steps until the credit arrives
Commercial and industrial installations
Larger plants follow the same steps at a bigger scale, with a few additions: a structural certificate for the roof, cable trays and combiner boxes for many strings, multiple inverters grouped near the array, an LT panel with protection relays, and remote monitoring at inverter or string level. Work is planned around the customer's operations — material lifts outside shift changes, tie-ins during a planned shutdown — and electrical-inspector approval is obtained before energisation. A punch list of minor items is closed before the final handover.
Safety on site
Rooftop work is done with fall protection on edges without parapets, ladders secured, tools tethered and no work during storms or rain. Panels generate DC voltage whenever light falls on them, so strings are kept isolated until testing, and connections are made with the DC isolator open. The customer's family or staff are kept clear of the work area, and the main power tie-in is done with the supply isolated. Sunvera's teams follow the same procedure on a 3 kW home and a 300 kW factory.
Common installation shortcuts — and why we avoid them
- Thin, painted mild-steel structures that rust within a few monsoons
- Household PVC wire instead of UV-rated solar DC cable
- Mismatched or poorly crimped connectors that overheat
- Skipping surge protection devices or sharing one poor earth pit
- Mounting the inverter on a sun-baked wall
- No string testing, so a dead string goes unnoticed for months
Each saves a little at installation and costs far more over 25 years. Call +91 77103 07937 to book a survey, or to have an existing system checked.
Frequently Asked Questions
One to two days on site for a home system, two to five days for a shop or office, one to two weeks for a school or society plant, and two to six weeks for a large factory plant. DISCOM inspection and net metering follow, usually within a few weeks.
Polarity checks, open-circuit voltage and current on every string, insulation resistance of DC cables, earth resistance of each pit, and an inverter functional and grid-synchronisation test including anti-islanding shutdown. Results are recorded in the commissioning report.
The inspector checks the system against the approved capacity, protection devices, earthing and anti-islanding, then the bi-directional meter is fitted. Sunvera attends and corrects observations; larger plants also need electrical-inspector approval before energisation.
A commissioning report with test results, panel and inverter serial numbers, invoices and warranties, a single-line diagram or as-built drawings, monitoring app access, owner training, and subsidy status for PM Surya Ghar projects.